Hanover Square Fountain Restoration

  • Project typeHanover Square Fountain Restoration
  • Project value+/- $1 Million
  • Contractor nameQPK Design
Street View Rendering

Project Location: Hanover Square Fountain, 110 S. Warren Street, 13202

Project scope: This project includes the rehabilitation and redesign of the existing fountain (see design renderings below).

Funding Source: Parks Capital Improvement Funds

Project Timeline: The timeline is subject to change due to contractor schedules, material availability and weather. 

  • Engagement Phase
    • An in-person engagement meeting will be held Monday, April 15, 4 - 7 p.m. in front of Hanover Square Fountain.  
  • Procurement Phase
    • Projected Start Date: Summer 2024
  • Construction Phase 
    • Projected Start Date: Spring 2025
    • Projected Completion Date: Spring/Summer 2025